Housing land
Where could Gedling’s new homes go?
The Council’s 2025 land assessment lists 277 sites with room for 26,566 homes. Only 5,639 of those are on sites it judges deliverable or developable within 15 years, and 17,932 (67%) are on Green Belt land, which covers 73% of the borough.
- 277
- SHLAA sites assessed
- 26,566
- homes they could hold
- 5,639
- on sites buildable within 15 years
- 73%
- of the borough is Green Belt (87.9 of 119.9 km²)
What the assessment concluded
A Strategic Housing Land Availability Assessment (SHLAA) is a council’s list of land that might take housing, each site with an estimated capacity and a verdict on whether and when it could be built. Gedling’s 2025 SHLAA layer gives five verdicts. Most of the capacity sits in the two that don’t count towards supply: “could be suitable” (usually needing a change of policy, such as release from the Green Belt) and “not deliverable or developable”.
- Deliverable now (0-5 years)131 sites4,339
- Developable in 6-10 years28 sites1,234
- Developable in 11-15 years9 sites66
- Could be suitable55 sites13,400
- Not deliverable or developable54 sites7,527
“Green Belt” means a point inside the site lies within the Local Planning Document’s Green Belt boundary. Capacities such as “Up to 300 homes” are counted at the upper figure.
On the map
Darker sites are judged buildable sooner. The large orange and grey blocks in the Green Belt are where the big numbers come from: 102 of the 277 sites lie in it.
The five biggest sites
Five sites account for 7,986 homes, 30% of the total. All five are in the Green Belt and none is judged buildable within 15 years. At the other end, 155 of the 277 sites hold ten homes or fewer.
| Site | Locality | Homes | Conclusion |
|---|---|---|---|
| Forest Farm G1178 | Papplewick | 2,585 | Not deliverable or developable |
| Land at New Farm, Redhill G1130 | Arnold | 2,300 | Could be suitable |
| Land to east of Teal Close G1262 | Carlton | 1,110 | Could be suitable |
| Springwater Golf Club G1374 | Calverton | 1,000 | Not deliverable or developable |
| Land off Lodge Farm Lane G462 | Arnold | 991 | Could be suitable |
Place by place
Carlton and Arnold carry 59% of the homes on sites buildable within 15 years. Papplewick has 2,638 homes of capacity on paper but only 5 on sites judged buildable.
- Carlton2,293 / 5,160
- Arnold1,036 / 5,807
- Hucknall924 / 2,746
- Calverton670 / 4,934
- Bestwood Village452 / 1,054
- Ravenshead155 / 2,599
- Newstead41 / 41
- Woodborough40 / 599
- Lambley12 / 636
- Burton Joyce10 / 335
- Papplewick5 / 2,638
- Linby1 / 17
What the plan already allocates
The Local Planning Document allocates 30 housing sites covering 164 hectares, and the Aligned Core Strategy adds 3 strategic sites: Teal Close (Carlton, 47.6 ha), Top Wighay Farm (Hucknall, 43.7 ha) and North of Papplewick Lane (Hucknall, 10.9 ha). The Brownfield Register 2025 lists 25 previously developed sites, 24.4 hectares in all, with room for 812 to 844 homes.
How this was worked out
- Sources: SHLAA 2025, Green Belt (LPD 12–15), housing allocations (LPD 64–70), strategic allocations (ACS 2), Brownfield Register 2025 and polling districts (merged, they give the borough outline: 119.9 km²).
- Capacity is read from the SHLAA’s text field (“40 homes”, “2,585 homes”, “Up to 300 homes”).
- “Buildable within 15 years” means the three conclusions that count towards supply: deliverable now (0-5 years), developable in 6-10 years, developable in 11-15 years.
- Areas are measured in British National Grid. One locality is misspelt in the source (“Lamlbey”) and is counted as Lambley.
- Script:
scripts/build-story-housing-land.py. Ask AI can reproduce any figure with SQL over the same layers.